Accredited project management training provider

Earned Value Management Glossary - Accredited Training Provider

Glossary of Key Terms:

ACWPActual Cost of Work Performed.The total costs incurred in accomplishing the work completed (usually cumulative to date, or any selected time period).
Apportioned Effort.Support tasks whose effort is planned and estimated as being directly proportional to the direct tasks being supported, e.g. Quality Assurance / inspection.
BACBudget at CompletionThe total value of budget (distributed) within the Performance Measurement Baseline (PMB). Equals sum of Control Account plans plus Planning packages where these are used. Where Fee is involved, this is usually outside of the PMB and therefore BAC.
BCWPBudget Cost of Work Performed ( aka Earned Value )The total budget value of the work performed (in any given time period). This is calculated by adding the sum of the budgets for completed work plus the completed portion of open work packages together with planned budgets for level of effort. This calculation can be made far simpler and more importantly far accurate (i.e. less prone to manipulation) by only including completed activities (or milestones).
BCWSBudget Cost of Work Scheduled ( aka  ‘ planned value’ )The sum of the authorised budgets for work planned to be have been completed plus the level of effort scheduled to be accomplished, usually to date, or any other given time period. Also referred to as ‘ planned value ‘.
CAControl Account A discrete WBS element of work extracted from the contract work breakdown structure with an agreed budget and schedule for the achievement of all tasks and objectives of the subject WBS element, which is assigned to a single person or party for execution and management – the Control Account Manager.
CAMControl Account ManagerResponsible for planning, co-ordination and achievement of all work within a control account (CA) work statement; he/she provides a single managerial focal point through which all schedule and cost issues pertaining can be addressed. The responsibilities of a CAM include:- Definition and agreement with the Project Manager the cost account work scope, schedule and budget.- Flowing down CA work scope to supporting departments, and tasking contributors via the agreement of work packages.
– Monitoring of all CA activities through the review of work packages and network reporting data, and providing status reports.
- Conducting formal cost and schedule variance analysis and in the development of any recovery plans required to recover schedule or cost variances.
CPICost Performance IndexThe cost performance index is the performance ratio comparing BCWP and ACWP, for any given period of time. (BCWP/ACWP)
CVCost VarianceThe difference between BCWP and ACWP for any given period of time. (BCWP-ACWP)
CWBSContract Work Breakdown StructureThe WBS for a specific contract (see WBS below).
Distributable BudgetThe sum of money, which is approved by Finance, and with which the functional areas finance the scope of work specified in their CAs.
EACEstimated Cost at CompletionThis is the statistical estimate of all costs at complete based upon current performance, calculated by taking actual direct costs allocated to the contract plus a forecast for costs of authorised work remaining based on cumulative performance to date. The most common method for developing EAC is:
EAC=ACWP+((BAC-BCWP)/ CPI), or BAC/CPI.
Other methods are also used including non-statistical Control Account Manager developed EACs.
EVAEarned Value AnalysisMeasuring and analysing performance by calculating Earned Value. This is the practice of determining how much of the contract budget has been ‘earned’ on the basis of the actual progress which has been made to date (regardless of the resources deployed to achieve this) and comparing this to the amount of cost incurred and to the planned value.
LoELevel of effortEffort (tasks) that is supportive (or managerial), which does not produce definitive end products. It is time oriented rather than output oriented, e.g. project management.
Master ScheduleA high level timetable of events (usually project milestones), which is agreed between the contractor and the customer for the schedule of deliverables within a programme. The master schedule is a summary plan which must be traceable to lower level schedule plans, i.e. at Work Package and Activity level.
Network (Critical path network)A logic flow diagram in a prescribed format consisting of activities and events which must be accomplished to reach programme objectives. It shows the planned sequence and interrelationships between work in the network.
LRELatest Revised EstimateThe contractors latest revised estimate of total costs at complete. This is the sum of the forecast of costs for all Control Accounts across the contract, as determined by the Control Account Managers.
OBSOrganisation Breakdown StructureA hierarchical structure for the project organisation detailing lines of responsibility through successive levels from senior managers to work package managers.
Planning PackagesFar term work and budget held in high level WBS elements to be planned in detail later downstream – only to be used where absolutely necessary.
PMBPerformance Measurement BaselineA stable time-phased budget plan, aggregated from the resources required to perform the schedule of work, against which cost and schedule performance is measured through the project life-cycle. The PMB excludes Fee and Management Reserve where these are used. The PMB should be maintained under formal change control.
RAMResponsibility Assignment MatrixA matrix formed by the allocation of cost accounts an OBS element, determining responsibilities for all work across the contract.
The ScheduleA timetable of start and finish dates for a list of activities. It is usually calculated from a network plan by a time analysis process, which uses the activity durations in conjunction with the specified logical constraints, resource allocations and availability.
To ScheduleThe process of calculating the optimum timeline using a critical path network plan including resource constraints and all major dependencies.
SoWStatement of WorkA description of the tasks to be carried out and the deliverables to be produced for any piece of work, e.g. Work Package or Control Account.
SPISchedule Performance IndexThe schedule performance index is the performance ratio comparing BCWP and BCWS for any given time period. (BCWP/BCWS)
SVSchedule VarianceThe difference between the BCWP and the BCWS for any given period of time (i.e. BCWP less BCWS).
TABTotal Allocated BudgetThe sum of the PMB + reserves, e.g., Management Reserve.
WBSWork Breakdown StructureA hierarchical structure which breaks down the work required to develop the main deliverable in the contract (and discharge all other contractual obligations) into successive levels of detail until the lowest level consists of readily manageable group of tasks, often referred to as Work Packages.
WPWork PackageA unit of work at the level where the work is performed and managed. A work package should have a relatively short time period, a budget expressed in money or labour units, a scheduled start and finish. It will, wherever possible, have a set of interim milestones that represent measurable points of physical accomplishment.

Email today to find out more on Earned Value Management.

Related Pages:

References

  • UK MoD Commercial Policy Guideline No.8 – Earned Value Management – Commercial Issues (Nov 2004)
  • US NDIA ANSI 748 – A Standard for Earned Value Management Systems – Intent Guide (Jan 2005)

Share this:

Testimonials

Contact Us Now

EMAIL us today.

Or call ++44 (0)1865 784040